Timeline

The following is a time line for the Feasibility Study

Phase & Tasks Tasks Current Status Target Date
Phase 1
1 Project Management Plan and Schedule The time frame is reviewed regularly. September 2005
2 Site and Technology Options Guiding Principles Draft approved for public exhibition July 2006
3 Preliminary Technical and Financial Assessment Draft in progress March 2007
4 Consultation with Community Reference Group (CRG) On going  
4a Community Engagement Commenced November 2006
Phase one completed
5 Preliminary Assessment of Sites and Technologies The consultants are currently testing the draft site selection criteria against the GIS system. December 2006
6 RRC Participant Consultation Stage One completed
Stage Two
May 2006
April 2007
Phase 2
7 Preferred Sites and technologies for the Project   May 2007
8 Waste Collection Systems Commenced November 2006
9 Financial Models Commenced March 2007
Phase 3
10 Staging of the Project   October 2007
11 Contract Delivery Mechanism Commenced October 2007
12 Business Plan, Participating Members' Agreement and Project Plan Commenced October 2007

City of Armadale City of Armadale City of Mandurah Shire of Murray Serpetine Jarrahdale Shire City of South Perth