The following is a time line for the Feasibility Study:
| PHASE AND TASKS | TASK | CURRENT STATUS | TARGET DATE |
|---|---|---|---|
| Phase 1 | |||
| 1 | Project Management Plan and Schedule | The time frame is reviewed regularly. | September 2005 |
| 2 | Site and Technology Options Guiding Principles | Draft approved for public exhibition | July 2006 |
| 3 | Preliminary Technical and Financial Assessment | Draft in progress | March 2007 |
| 4 | Consultation with Community Reference Group (CRG) | On going | |
| 4a | Community Engagement | Commenced | November 2006 Phase one completed |
| 5 | Preliminary Assessment of Sites and Technologies | The consultants are currently testing the draft site selection criteria against the GIS system. | December 2006 |
| 6 | SEMRC Participant Consultation | Stage One completed Stage Two |
May 2006 April 2007 |
| Phase 2 | |||
| 7 | Preferred Sites and technologies for the Project | May 2007 | |
| 8 | Waste Collection Systems | Commenced | November 2006 |
| 9 | Financial Models | Commenced | March 2007 |
| Phase 3 | |||
| 10 | Staging of the Project | October 2007 | |
| 11 | Contract Delivery Mechanism | Commenced | October 2007 |
| 12 | Business Plan, Participating Members' Agreement and Project Plan | Commenced | October 2007 |